Minor construction work begins in Lakeview Estates May 21, 2019

Post Date:05/06/2019 3:43 PM

As a follow up to last year’s construction in Lakeview Estates, Lac La Biche County began cleanup in the subdivision last week. Minor construction work, including paving repairs and replacing one culvert, is scheduled to begin after the May long weekend. 

Timeline:                     May 21, 2019 to June 7, 2019
Scope of Work:          Paving Approaches & Culvert Replacement
Hours of Work:           7:00 a.m. to 5:30 p.m, 7 days a week

Impact to Residents and Local Traffic:

  • The County’s contractor Camp 5 will begin paving repairs on Tuesday, May 21, 2019.
  • Utilizing day labour, replacement of the culvert on the northern approach into Lakeview Estates is also scheduled for Tuesday, May 21, 2019. Subdivision access at Lakeview Drive will be closed for the duration of the project.
  • There will be no interruptions to services, including waste and recycling pick-up.

We will endeavor to maintain safe work practices to ensure there is no injury to persons or damage to property. We ask that all residents maintain a safe buffer from construction activities, and ensure that animals and children are kept away from the site. Please obey all construction signage and personnel.

We appreciate your patience and cooperation as we complete this important work. If this schedule changes, we will provide updates to all residents.  If you have any questions or concerns, please contact Ali Memon, Manager of Engineering Services, at 780-623-6801, or the undersigned.

Dylan Maskalyk
Engineering Technologist, Lac La Biche County
Phone: 780-623-6821
dylan.maskalyk@laclabichecounty.com