Current Construction Projects

Print
Press Enter to show all options, press Tab go to next option

Lac La Biche County undertakes a wide variety of construction and engineering projects each year. These projects expand and improve our County's infrastructure, to better serve our residents and visitors.

Below is a summary of ongoing construction projects. Lac La Biche County works to ensure the information on this page is accurate and up to date, but please note that project scopes and timelines may change for a variety of reasons. For more complete project details, please call (780) 623-1747 and ask to speak to the department in charge of the project you're interested in.

Last updated: September 24, 2020. Project information will be updated regularly (weekly or monthly, depending on the specific project).

2019 Carryover Projects and New 2020 Construction Projects

Project Location Project Timeline and Status Consultant Construction Company County Department In Charge

104 Street Water & Sewer Rehabilitation - 225 metres

104 Street in the hamlet of Lac La Biche Complete. Stantec E Construction Engineering Services

Lakeview Crescent Water & Sewer Replacement

Click here to read the project Notice of Construction

Lakeview Crescent, hamlet of Lac La Biche

Project is in progress. Final phase is expected to be complete in October 2020.

V3 Companies

Thompson Infrastructure Ltd.

Engineering Services

Plamondon-Caslan Connector (North) Base & Pave

Range Road 162 (Plamondon-Caslan Connector) from Highway 55 to Township Road 670 (approx. 6.5 km)

Complete. WSP Carmacks Engineering Services
Craigend Grader Shop

Intersection of Highway 55 and Range Road 134, across from Craigend Hall

Complete.

Richards Consulting In-house Engineering Services

Mystic Beach Access Road - Township Road 682A

From the paved section of Township Road 682A to the intersection with Highway 881 Complete. WSP

Allied Paving Co. Ltd. / Location Cats

Engineering Services

County Centre Shop Expansion (Phase 3)

Lac La Biche County Centre property, southeast of the hamlet of Lac La Biche

Project is in progress. Expected completion date is September 2021.

Richards Consulting TBD Engineering Services

County Centre Parking Lot & Yard Extension

Lac La Biche County Centre property, southeast of the hamlet of Lac La Biche

Project is in design stage. Construction starts in 2021. Stantec Day labour Engineering Services

Highway 881 Crosswalk Lighting

Intersection of Highway 881 and Lac La Biche County Centre property's western access

Project is in design stage. Construction starts in 2021. In-house Day labour Engineering Services

Bold Center Sports Fields

Immediately east of the Bold Center, in the hamlet of Lac La Biche.

Artificial turf field and track: Expected completion in August 2020

Natural track: Expected completion in summer 2021.

Lombard North Group Wilco Phase 1 Parks & Facilities

Beaver River Bridge Replacement

Township Road 653 (Christy Creek Road), approx. 4 km west of Highway 36 Complete.  WSP Formula Alberta Ltd. Engineering Services

Lac La Biche Golf Course Pump House

Lac La Biche Golf & Country Club property Summer 2020 WSP AP Irrigation Parks & Facilities

Campsite Road Boat Launch

Reclamation of existing boat launch at Plamondon Whitesands Resort, and construction of new boat launch at Plamondon Motor Sports Club property.

Reclamation work to start July 15. Construction expected to take place in summer of 2020, dependent on approvals. Green Plan TBD Parks & Facilities

Poplar Point Boat Launch

Poplar Point, at the south end of Range Road 144. Construction to start in August 2020. Green Plan Day Labour Parks & Facilities

Holowachuk Estates boat launch improvements

North shore of Beaver Lake, at Birch Drive Construction to start July 15. In-house Day Labour Parks & Facilities

Owl River Boat Launch

Owl River, north of Lac La Biche Lake Construction expected to take place in fall 2020

Lombard North Group

TBD Parks & Facilities

Protective Services Building Underground Work

Protective Services Building (located southwest of the Beaver Hill Road and Nipewon Road intersection) Complete.   Thompson Infrastructure Ltd. Engineering Services

 Bridge File 294: Culvert Replacement 

On RR 113 Between TWP RD 642 & 645  In progress. Construction to start and finish in Oct. 2020  WSP Urlacher Construction Engineering Services

 Compost Pad

 Beaver Lake Landfill

In progress. Expected to be complete by end of 2020.

In-house  In-house

Environmental and Engineering Services

2020 Construction Programs

These programs will improve infrastructure in multiple locations throughout the County.


Program

Timeline Consultant
Construction Company
County Department In Charge

Sidewalk Replacements

Complete. In-house Signature Contractors Transportation Services

Hamlet Road Resurfacing

Complete. In-house.

Camp 5 Paving

Transportation Services

Walking Trail Resurfacing

TBD TBD TBD Parks & Facilities

Outdoor Rink Resurfacing

TBD In-house In-house Parks & Facilities

Bridge Structure Replacements

Ongoing engineering. WSP TBD Engineering Services

 

2020 Engineering-Only Projects (No construction)

Project
Location
Timeline
Consultant


County Department In Charge

Sentinel Industrial Park Water & Sewer Lines

Sentinel Industrial Park In progress MPE Engineering Services

Sentinel East Storm Pond

Sentinel Industrial Park

In progress

S. E. Design Engineering Services

95 Street Water & Sewer

Hamlet of Lac La Biche

On hold

V3 Companies of Canada

Engineering Services

101 Avenue Water & Sewer

Main Street, hamlet of Lac La Biche

On hold V3 Companies of Canada Engineering Services

Campsite Road Paving

North of the hamlet of Plamondon

On hold Stantec

Engineering Services

Subdivision Paving/Engineering

Golden Sands, Pleasant Acres, Young's Beach, John Martin and Sunset Bay

Engineering in progress.

WSP, WOOD, Stantec

Engineering Services