This year’s capital budget lays a foundation for the future, with construction beginning on a $15 million Aquatics Centre at the Bold Center and a $20 million Main Street Lac La Biche revitalization project—both developments will be completed over multiple years. A further $5.4 million will be spent to finish the last phase of the Bold Center Sports Fields project, and $2.7 million (of which 73% is grant-funded) will be used to replace 5 bridges and large culverts. Lift stations will be built near Plamondon for $2 million to improve sewer services in the area.
2021 Capital Project Overview:
2021 Construction Project Overview:
For a complete list of construction projects planned for this budget year, please click on Project Overview.
Construction Notices:
- Feb. 1/21: Construction Notice for Bridge File 13640 – Nashim Drive
- Feb. 24/21: Construction Notice for the Blais Resort Storm Outfall, Feb. 25-Apr. 9 (also linked in the table below)
- Mar. 5/21: General Notification Letter for the 101 Avenue Surface and Utility Rehabilitation (also linked in the table below)
- Mar. 8/21: Pre-construction Notice for Plamondon Lift Stations - Tree Clearing & Borehole Drilling (also linked in the table below)
2020 Carryover & 2021 Construction Projects:
Project | Location | Timeline | Consultant | Construction Company |
County Department In Charge |
Bold Center Projects: | |||||
Bold Center Sports Fields Phase 2: Developing artificial and natural turf playing fields and an eight-lane track. |
Artificial turf field and track: Expected completion date is June, 2021. Natural track: Expected completion date is June, 2021. |
Immediately east of the Bold Center, in the hamlet of Lac La Biche. |
Lombard North Group |
Wilco | Parks & Facilities |
Bold Center Sports Fields Phase 3: Construct a facility to include change rooms and concession to service the sports fields. |
Project is in progress. Expected completion date is September, 2022. |
||||
Bold Center Campground, Equipment, Basketball and Tennis Courts | Immediately east of the Bold Center in the hamlet of Lac La Biche, adjacent to planned sports fields. |
Project is in progress. Expected completion date is June, 2021. |
Lombard North Group |
TBD | Parks & Facilities |
Bold Center Lounge Renovations |
Lac La Biche | Spring 2021 | TBD | TBD | Parks & Facilities |
Plamondon Arena Exterior Wall Siding Upgrades |
Plamondon | Summer 2021 | In-house | Day Labour | Parks & Facilities |
Community Garden Relocation | TBD | Project is in design stage. Future construction timeline TBD. |
TBD | TBD | Parks & Facilities |
Bridge File 77865 | Campsite Road | Project is in progress. Expected completion date is September, 2021. |
Stantec | TBD | Engineering Services |
Bridge File 74197 | Old Highway 46 | Project is in progress. Expected completion date is September, 2021. |
Wood | TBD | Engineering Services |
Bridge File 79415 | Over Gold River | Project is in progress. Expected completion date is September, 2021. |
WSP | TBD | Engineering Services |
Bridge File 72757 | Over Missawawi Creek | Project is in progress. Expected completion date is September, 2021. |
WSP | TBD | Engineering Services |
Bridge File 13640 | Nashim Drive | Project is completed, as of Mar. 5/21. Was scheduled for completion in September, 2021. |
WSP | TBD | Engineering Services |
Bayview Beach Water & Sewer | Bayview Subdivision | Project is in progress. Expected completion date is October, 2021. |
Stantec | TBD | Engineering Services |
Sentinel East Storm Pond | Sentinel Industrial Park, approx. three kilometres west of the hamlet of Lac La Biche and immediately north of Highway 55. |
In progress. Expected completion is November, 2021. |
S.E. Design | TBD | Engineering Services |
101 Avenue Surface and Utility Rehabilitation | Main Street Lac La Biche from 103 St. to 105 Street. |
Project is in progress. Expected completion date of phase 1 is November, 2021. |
V3 Companies of Canada |
TBD | Engineering Services |
County Centre Shop Expansion (Phase 3) |
Lac La Biche County Centre property, southeast of the hamlet of Lac La Biche. |
Project is in progress. Expected completion date is September, 2021. |
Richards Consulting |
Vantage Builders | Engineering Services |
County Centre Parking Lot & Yard Configuration including Chemical Storage Shed/ Warehouse. |
Lac La Biche County Centre property, southeast of the hamlet of Lac La Biche. |
Project is in design stage. Future construction timeline TBD. |
Stantec | TBD | Engineering Services |
Highway 881 Crosswalk Lighting | Intersection of Highway 881 and County Centre west access. |
Project is in design stage. Future construction timeline TBD. |
Stantec | TBD | Engineering Services |
Beaver Lake Lift Station Upgrades (generator/pump) | North side of Beaver Lake | Project is in progress. Expected completion date is September, 2021. |
Associated Engineering |
TBD | Engineering Services |
Plamondon Wastewater Lift Stations (2) | Plamondon/Mission Road | Project is in design stage. Future construction timeline TBD. |
MPE Engineering | TBD | Engineering Services |
BNR Plant - Hydrovac receiving station BNR Plant - Bio-Train Covers BNR Lift Station - Muscle Wall Kit - Emergency Dyke System |
Range Road 141 / Township Road 670 |
Project is in progress. Construction expected completion date is October, 2021. |
In-house | Day Labour | Utilities |
Natural Gas Rehabilitation - 104 Street Backlane - Steel Gas Line Replacement |
Lac La Biche | Construction expected to take place in spring 2021. |
TBD | Lac La Biche Natural Gas Coop |
Engineering Services |
Utility Yard Pole Shed | Lac La Biche | Construction expected to take place in spring 2021. |
TBD | TBD | Utilities |
Rich Lake Area Sani Dump |
North of Rich Lake at RR 114. | Construction expected to take place in summer 2021. |
TBD | Day Labour | Engineering Services |
Protective Services Facility: |
Engineering Services |
Immediately southeast of the Bold Center in the hamlet of Lac La Biche. |
Summer 2021 | In-house | Signature Contracting |
Parking lot paving. | |||||
Fork Lake Access, Parking and Washrooms | SE of Rich Lake at Fork Lake Boat Launch off Highway 867. |
Construction expected to resume in spring of 2021. |
In-house | Day Labour | Parks & Facilities |
McArthur Park Staircase by Gazebo | Lac La Biche | Construction expected to resume in spring of 2021. |
In-house | Day Labour | Parks & Facilities |
Alexander Hamilton Park Washroom and Trail Paving | Lac La Biche area. | Construction resume to take place in spring of 2021. |
In-house | Day Labour | Parks & Facilities |
Boat Launch/Access Projects: |
|||||
Campsite Road Boat Launch: | Boat launch reclamation: Plamondon Whitesands Resort on Campsite Road. |
Construction expected to resume in summer of 2021, dependent on approvals. |
TBD | TBD | Parks & Facilities |
Reclaiming the boat launch at Plamondon Whitesands Resort and constructing a new launch nearby on Campsite Road. |
Boat launch construction: Plamondon Motor Sports Club property on Campsite Road. |
||||
Holowachuk Municipal Reserve Beach Access with Stairs |
Beaver Lake | Construction expected to resume in summer of 2021. |
In-house | Day Labour | Parks & Facilities |
Owl River Boat Launch and Campground |
North end of Lac La Biche Lake |
TBD | TBD | Day Labour | Parks & Facilities |
Elinor Lake Boat Launch Parking | South of Elinor Lake Resort. | Expected completion date is August, 2021. |
TBD | Day Labour | Engineering Services |
Blais Resort Drainage/Campsite Road Boat Launch |
Blais Resort Subdivision | In progress. | Stantec | TBD | Engineering Services |
Compost Pad at Beaver Lake Landfill |
Beaver Lake | TBD | TBD | TBD | Environmental Services |
Beaver lake Landfill Fence Upgrade |
Beaver Lake | TBD | TBD | TBD | Environmental Services |
Tire Bunker at Craigend Transfer Station |
Craigend | TBD | TBD | TBD | Environmental Services |
Access Matting for Landfills |
Beaver Lake and Plamondon |
TBD | TBD | TBD | Environmental Services |
Slope Repair at Beaver Lake Landfill |
Beaver Lake | TBD | TBD | TBD | Environmental Services |
Poplar Point Boat Launch: Municipal Beach Access, on the north shore of Lac La Biche Lake. |
Parks & Facilities |
Poplar Point, at the south end of Range Road 144. |
Construction expected to take place in summer of 2021. |
In-house | Day Labour |
2021 Construction Programs |
These programs will enhance infrastructure in multiple locations throughout the County. |
Program | Timeline | Consultant | Construction Company |
County Department In Charge |
Outdoor Rink Resurfacing |
TBD | In-house | In-house | Parks & Facilities |
Hamlet Back Lane Paving |
Summer 2021 | in-house | TBD | Engineering Services |
Walking Trail Resurfacing: Golf Course Cart Trail, Mission |
Summer 2021 | Wood | TBD | Transportation Services |